Estimating · Templates

Roof replacement scope of work: a section-by-section template for roofers

A copy-paste roof replacement scope, unit prices for what you can't see until tear-off, exclusions and assumptions, a sample hidden-conditions note for your attorney, three client texts and two AI prompts that organize the paperwork while you set every number.

BuildFlow AI · November 18, 2026 · About an 8-minute read

A roofing estimate often fits on one line: "Tear off and replace roof, architectural shingles." Then the questions start. Does that include the garage? What happens if the decking is rotted? Are the gutters coming off? Who pays for the second layer nobody knew about? A written scope answers those before the client signs, and it's what turns a surprise at tear-off into a change order instead of free work.

Not legal or code advice. This is general business information. Building codes, underlayment and ice barrier requirements, permits, manufacturer warranty terms, insurance rules, HOA rules and contract requirements vary by location. Check with your local building department, and have a local construction attorney review your contract, scope notes and any clause language before you use them.

01Why a roof needs a written scope

Roofing has a blind spot most trades don't: you can't see the decking, the number of layers or the condition around a chimney until the old roof is already off. By then the house is open and the client is watching the weather.

That's the worst moment to negotiate. If the scope already says how decking is priced, what an extra layer costs and what happens when something else turns up, the conversation is a text with photos instead of an argument.

A scope of work names every part of the job and says whether it's included, excluded, priced by the unit or based on an assumption. When an assumption turns out wrong, you have an agreed reason to write a change order.

02The section-by-section scope template

Copy this into your estimate and fill in the brackets. Delete what doesn't apply. Measurements, products and code details are yours to set per local code and the manufacturer's instructions; the template only gives the sections.

ROOF REPLACEMENT SCOPE OF WORK Client: [name] · Address: [address] Roof areas included: [main house / garage / porch / additions] Approx. size: [ ] squares (to be confirmed) · Pitch: [ ] · Stories: [ ] 1. PROTECTION & SETUP - Dumpster / trailer location: [driveway / street], driveway protection [method] - Protect landscaping, AC units, windows and siding near drop zones: [method] - Attic items: client to move stored items under the roof deck [Y/N] 2. TEAR-OFF - Remove [ ] layer(s) of existing roofing down to decking - Remove existing underlayment, flashing, vents and pipe boots: [list] 3. DECKING - Inspect decking after tear-off; photos sent to client - Damaged decking replaced at $[ ] per sheet ([size/type]); count confirmed in writing - Re-nail or other decking work per local code: [included / priced separately] 4. UNDERLAYMENT & EDGES - Underlayment: [type / product line] - Ice barrier at [eaves / valleys / other], where required by local code or as listed - Drip edge at [eaves / rakes], color [ ] 5. FLASHING - Step and counter flashing at walls: [new / reuse where sound] - Chimney flashing: [new / reflash / excluded]; masonry repair excluded unless listed - Skylights: [reflash / replace / excluded] 6. VALLEYS - Valley method: [open metal / closed / woven], per manufacturer instructions 7. VENTILATION - Ridge vent / box vents / other: [list, quantity] - Intake (soffit) vents: [existing / added / excluded] - Pipe boots and other penetrations: [count, type] 8. ROOFING - Product: [manufacturer / line / color] installed per manufacturer instructions - Starter, hip and ridge: [product] - Manufacturer warranty registration: [who / which program] 9. GUTTERS & EXTRAS (only what's priced) - Gutters / downspouts: [detach and reset / replace / excluded] - Satellite dish, solar, antennas: [detach and reset by others / excluded] 10. PERMITS, INSPECTIONS, CLEANUP - Permits pulled by [ ], fees paid by [ ] - Inspections: [as required locally] - Daily cleanup; final magnet sweep of driveway, lawn and beds; haul-away

A few notes on the sections that cause the most back-and-forth:

  • Roof areas. List every section included: main roof, garage, porch, additions. "The roof" means different things to different people.
  • Decking. You can't see it until tear-off. Put a per-sheet price in the scope so the client agrees to the rate before anyone sees the boards.
  • Flashing. Say whether wall, chimney and skylight flashing is new or reused, and that masonry repair isn't included unless it's listed.
  • Things on the roof. Satellite dishes, solar panels and antennas: say who detaches and resets them, or that it's by others.
  • Permits. Name who pulls the permit and who pays the fee.

Pricing the job? The remodeling estimate template shows where this scope goes alongside payment terms and an expiration date, and the payment schedule template shows how to tie payments to finished milestones.

03Unit prices for hidden decking

You can't count rotted decking from the driveway. Instead of guessing a number into the price, list a unit price in the scope and bill the actual count with photos. The client agrees to the rate up front, and the count is just documentation.

UNIT PRICES (EXAMPLE ONLY: these numbers are placeholders, not recommended prices) - Decking replacement: $[ ] per sheet, installed e.g. "Decking: 6 sheets replaced x $[ ] = $[ ]" (photos attached) - Fascia replacement: $[ ] per linear foot - Additional roofing layer removal: $[ ] per square Counts are confirmed in writing, with photos, before the final invoice.

The numbers above are placeholders to show the format. Use your own pricing. Keep the unit, the photo requirement and the written confirmation. The same idea works for remodeler allowances; see remodeling allowances and overages.

04Exclusions and assumptions

Exclusions say what the price doesn't cover. Assumptions say what the price depends on. On a roof, most of the risk sits in the assumptions about layers, decking, access and weather.

EXCLUSIONS (examples; keep only what fits your job) - Rafter, truss, fascia or soffit repair unless listed or priced by unit - Chimney masonry, crown or chase repair - Interior repairs (drywall, paint, stains) from past or existing leaks - Gutters, gutter guards or downspouts unless listed - Detaching or resetting solar, satellite or antennas (by others) - Insulation, attic bath fan or dryer vent rework unless listed ASSUMPTIONS (examples) - Existing roof has [ ] layer(s); more layers found = change order - Decking is [plank / sheet]; switching to sheet decking = priced separately - Dumpster and material delivery can reach [location] - Work is weather-dependent; the roof is protected at the end of each day - Client selects product and color by [date]

Read these lists with the client when you review the estimate, and photograph the house before you start: the existing roof, gutters, driveway, landscaping and any interior ceiling stains. See jobsite photo documentation for a simple way to file them by job.

05Hidden conditions: a sample scope note

A short note explaining what happens when you find something you couldn't see helps. Here is sample language to take to your attorney. It is not a finished contract clause.

SAMPLE SCOPE NOTE: HIDDEN CONDITIONS (have your attorney review) "The price above is based on the roof as it could be inspected before tear-off and the assumptions listed. Decking replacement is billed at the unit price above, with photos and a count. If we find conditions beyond that, such as additional roofing layers, damaged rafters or fascia, or rot around a chimney or skylight, we will show you what we found and provide a written change order with price and schedule impact before that work starts. We will protect the roof while we wait for your written approval."

Attorney note: this is sample language for discussion only. Have a local construction attorney review and adapt it, along with your contract and change order form, before you use it.

When a hidden condition does show up, write the change order before the extra work starts. The change order template covers scope, price, schedule impact and written approval, and how to price extra work walks through pricing it line by line. A free sample change order prompt is on /packs (no email needed), and the free clause and text script is at /free.

06Three copy-paste client texts

Fill in the brackets and send. They work as emails too.

1. After the site visit

Hi [client first name], thanks for meeting me today. Before I price the roof I want to confirm: which areas we're replacing (house, garage, porch), the product and color you're leaning toward, whether gutters are part of it, and anything on the roof that needs to come off and go back (satellite, solar, antennas). I'll have the scope and estimate to you by [day].

2. The day before tear-off

Hi [client first name], we're scheduled to start your roof on [date], weather permitting. The dumpster will go [location]. Please move cars out of the driveway, and if you have things stored in the attic right under the roof, cover or move them, because some dust and nails can come through during tear-off. If rain is in the forecast, I'll text you the night before.

3. After tear-off: decking found

Hi [client first name], the old roof is off. We found [number] sheets of decking that need to be replaced. Photos attached. Per the scope, that's $[ ] per sheet, so $[ ] total. [If something beyond the unit prices:] We also found [condition] that isn't in the price. I'll send a written change order with price and schedule impact, and the roof stays protected until you approve it.

07Two AI prompts

Paste these into ChatGPT, Claude or Gemini with only what you actually know. AI is good at organizing site notes and catching gaps. It should never set your prices, measure the roof or decide code and warranty questions. Read every output before you send it.

Prompt 1: roof scope from inspection notes

Act as an estimator for a small residential roofing company. Using ONLY my inspection notes below, write a roof replacement scope of work organized in this order: protection and setup, tear-off, decking, underlayment and edges, flashing, valleys, ventilation, roofing product, gutters and extras, permits, inspections and cleanup. For each, write what's included in plain language. Then list likely exclusions and assumptions based only on what I described. Do NOT add prices, quantities, measurements, products, code requirements or warranty terms I didn't mention. Mark anything you need from me with [CHECK]. Inspection notes: [paste or dictate: roof areas, layers, pitch, chimney/skylights, vents, gutters, attic notes, client wishes]

Prompt 2: review the scope for gaps

Review this roof replacement scope before I price it. Using ONLY the text I paste, list: (1) anything a homeowner might assume is included that isn't stated either way (gutters, skylights, chimney work, interior repairs, haul-away), (2) hidden-condition items without a unit price (decking, fascia, extra layers), (3) items not assigned to anyone (permits, solar or satellite reset, dumpster placement), (4) anything about weather or protection of an open roof that's missing. Don't add prices or code requirements. Just list the gaps so I can decide. Scope: [paste]

More estimating prompts are in AI prompts for construction estimators. Doing other exterior work? The deck scope template follows the same format, and so do the basement, kitchen and bathroom templates.

AI Estimator Pack · $47

Scopes, leveled sub bids and a proposal letter from your site notes

The AI Estimator Pack has copy-paste prompts and workflows for scopes by trade, takeoff checklists, sub bid leveling, pricing extras with your own rates, bid cover letters, estimate review and follow-ups, plus a spreadsheet template. AI organizes the paperwork. You set every number. One-time price.

Or start with the free change order prompt, see every pack on /packs, or get the All-Roles Bundle for $127.

08FAQ

What should a roof replacement scope of work include?

Which roof areas are included, how many existing layers come off, how damaged decking is handled and priced, underlayment and any ice barrier, drip edge, flashing at walls, chimneys and skylights, valleys, vents and ventilation, the roofing product and color, gutters, permits, inspections, cleanup and disposal, plus exclusions and the assumptions your price depends on.

How should I price decking replacement I can't see until tear-off?

Many roofers list a unit price per sheet of decking (and sometimes per linear foot of fascia or rafter repair) in the scope, so the client agrees to the rate before tear-off. Then document what you replace with photos and a count, and confirm the total in writing. Set your own rates, and check your local and state requirements.

Should the scope say what happens if it rains mid-job?

Yes. Say how you protect an open roof, that weather can shift the schedule, and how the client will be told about delays. It keeps a rain day from turning into a dispute about timelines.

Write down what's in, what's out, and what the decking costs. Then tear it off.

Start with the free change order prompt, download the clause and text script at /free, see every role pack at /packs/, or get the full workflow.

Free: change order prompt

Paste it into ChatGPT, Claude or Gemini with your job note and get a short change order draft. No email needed. The free clause and text script is here.

Get the free prompt

The AI Estimator Pack

Scopes, takeoff checklists, sub bid leveling, pricing extras, cover letters and estimate review. $47, one time.

Estimator Pack · $47

The AI Change Order Pack

Prompts, the editable template, approval texts and the manual and automated setups. $47, one time.