Home addition scope of work: a phase-by-phase template for builders and remodelers
A copy-paste home addition scope, unit prices for what you find at the tie-in, exclusions, a sample note for your attorney, three client texts and two AI prompts. You set every number.
BuildFlow AI · November 23, 2026 · About a 9-minute read
An addition estimate can look complete and still leave the biggest questions open. Who draws the plans? What if permit review asks for changes? Is the existing panel big enough? What if the wall you open has water damage behind it? A written scope answers those before the client signs, and turns a surprise at the tie-in into a change order instead of free work.
Not legal or code advice. This is general business information. Building codes, zoning setbacks, permits, engineering requirements, HOA rules and contract requirements vary by location. Check with your local building and zoning departments, use a licensed design professional or engineer where your jurisdiction requires one, and have a local construction attorney review your contract, scope notes and any clause language before you use them.
01Why additions need a written scope
An addition is new construction attached to an old house. The new part is on the plans. The old part is whatever you find when you open the wall, pull back the roof and trace the circuits.
That's where disputes start. The client sees a new room. You see design, permits, foundation, framing, a tie-in, several trades and finish work blending into rooms you weren't hired to remodel. If the scope doesn't say where your work in the existing house starts and stops, the client will assume it covers whatever looks connected.
A scope of work names every phase, says who is responsible for each part, and states the assumptions your price depends on. When something changes, you point to the line and write a change order.
02The section-by-section scope template
Copy this into your estimate and fill in the brackets. Delete what doesn't apply. Dimensions, products, engineering and code details are yours to set with your designer, engineer and local building department; the template only gives the sections.
HOME ADDITION SCOPE OF WORK
Client: [name] · Address: [address] · Year built: [ ]
Addition: [type] · Approx. size: [ ] sq ft · Plans by [ ], dated [ ], rev. [ ]
1. DESIGN, ENGINEERING & PERMITS
- Engineering (if required) by [ ], paid by [ ]
- Zoning / HOA check by [ ]; permit pulled by [ ], fees paid by [ ]
- Plan changes after permit review = written change order
2. SITE PREP & PROTECTION
- Utility locate by [ ]; equipment access: [ ]
- Lawn / landscaping protection: [method]; removals: [listed / excluded]
3. EXCAVATION & FOUNDATION
- [Slab / crawlspace / basement / piers] per plans, incl. waterproofing
- Rock, groundwater or buried items = change order; spoils: [hauled / on site]
4. FRAMING per plans (floor, walls, roof, sheathing, beams)
5. TIE-IN TO EXISTING HOUSE
- Open existing wall at [location]; roof tie-in and flashing at [location]
- Temporary weather protection while open: [method]
- Hidden-condition repair at the unit prices below
6. ROOFING & EXTERIOR
- Roofing, windows, exterior doors, siding and trim per schedule
- Gutters: [new / extend / excluded]; match to existing: [best effort]
7. MECHANICAL, ELECTRICAL & PLUMBING (licensed trades)
- Electrical per plan; panel capacity: [checked / upgrade priced separately]
- Plumbing (if any) per fixture schedule
- HVAC: [extend existing / new system]; capacity checked by [ ]
8. INSULATION, DRYWALL & FINISHES
- Insulation and air sealing per local energy code (confirm locally)
- Drywall finish level [ ]; trim [profile]; paint: [included / excluded]
- Flooring and fixtures per allowances below
9. BLENDING INTO THE EXISTING HOUSE
- Patch and paint disturbed existing walls: [rooms / limit]
- Existing flooring, trim or siding repair limited to [ ]
10. CLEANUP & CLOSEOUT
- Daily cleanup; dumpster at [ ]; grading: [rough / finish]; seed / sod: [Y/N]
- Punch walkthrough and closeout documents
A few notes on the sections that cause the most back-and-forth:
Design responsibility. Say who draws the plans, who provides engineering if required, and what happens when plans change after permit review.
The tie-in. This is where most hidden conditions show up. Put unit prices in the scope so the client agrees to the rate before the wall is opened.
Existing systems. State whether the electrical service and HVAC have been checked for the new load. If an upgrade might be needed, price it separately or exclude it.
Pricing the job? The remodeling estimate template shows where this scope goes alongside payment terms and an expiration date, and the payment schedule template shows how to tie payments to finished milestones like foundation, dry-in and final.
03Unit prices and allowances
You can't see inside the existing wall until it's open, and selections may not be made at signing. List unit prices for common tie-in repairs and allowances for selections, then bill the actual count with photos.
UNIT PRICES (EXAMPLE ONLY: these numbers are placeholders, not recommended prices)
- Existing wall framing repair at the tie-in: $[ ] per linear foot
- Existing roof decking replacement at the tie-in: $[ ] per sheet
- Additional excavation beyond plan depth: $[ ] per [cubic yard / hour]
e.g. "Decking at tie-in: 3 sheets x $[ ] = $[ ]" (photos attached)
ALLOWANCES (EXAMPLE ONLY: placeholders, not recommended amounts)
- Flooring: $[ ] per sq ft, material only
- Lighting fixtures: $[ ] total
Overages and counts are confirmed in writing, with photos.
The numbers above are placeholders to show the format. Use your own pricing. Keep the unit, the photo requirement and the written confirmation. See remodeling allowances and overages, and tie selection deadlines to the schedule with the selection schedule template.
04Exclusions and assumptions
Exclusions say what the price doesn't cover. Assumptions say what it depends on: on an addition, mostly the plans, the soil, the tie-in and existing systems.
EXCLUSIONS (examples; keep only what fits your job)
- Work in the existing house not listed above
- Electrical service or HVAC upgrades unless listed
- Sewer, water, gas or septic relocation
- Rock, unsuitable soil or groundwater control
- Hazardous material testing or abatement
- Exact match of existing siding, roofing, flooring or paint
ASSUMPTIONS (examples)
- Price is based on plans dated [ ]; changes = change order
- Existing framing at the tie-in is sound; repairs at unit prices
- Existing systems can carry the new load unless noted
- Client makes selections by the dates in the selection schedule
A short note explaining what happens when you find something you couldn't see helps. Here is sample language to take to your attorney. It is not a finished contract clause.
SAMPLE SCOPE NOTE: HIDDEN CONDITIONS AND THE EXISTING HOUSE (have your attorney review)
"The price above is based on the plans listed, the existing house as it could be inspected before work started, and the assumptions listed. Repairs we find when we open the existing wall or roof are billed at the unit prices above, with photos and a count. If we find conditions beyond that, such as damaged framing, wiring that has to be updated, water damage or unsuitable soil, we will show you what we found and provide a written change order with price and schedule impact before that work starts. We will keep the house weather-tight while we wait for your written approval."
Attorney note: this is sample language for discussion only. Have a local construction attorney review and adapt it, along with your contract and change order form, before you use it.
When a hidden condition does show up, write the change order before the extra work starts. The change order template covers scope, price, schedule impact and written approval, and how to price extra work walks through pricing it line by line. A free sample change order prompt is on /packs (no email needed), and the free clause and text script is at /free.
06Three copy-paste client texts
Fill in the brackets and send. They work as emails too.
1. After the site visit
Hi [client first name], thanks for walking the house with me today. Before I price the addition I want to confirm who is drawing the plans, what the room is for, where it connects to the house, and whether anything in the existing house is part of the job (paint, flooring, the electrical panel, heating and cooling). I'll have the scope and estimate to you by [day].
2. The day before the tie-in
Hi [client first name], we're set to open the existing wall on [date], weather permitting. Please clear [rooms] by [time]. We'll put up dust walls and floor protection, and the house will be weather-tight at the end of each day. Once the wall is open I'll send photos of what we find.
3. After opening the existing wall: damage found
Hi [client first name], we opened the wall where the addition connects. [What you found, e.g. "Two studs have water damage."] Photos attached. Per the scope, framing repair at the tie-in is $[ ] per linear foot, about $[ ] total. [If beyond the unit prices:] We also found [condition]. I'll send a written change order with price and schedule impact, and the house stays weather-tight until you approve it.
07Two AI prompts
Paste these into ChatGPT, Claude or Gemini with only what you actually know. AI is good at organizing site notes and catching gaps. It should never set your prices, measure the job or decide code, engineering and warranty questions. Read every output before you send it.
Prompt 1: addition scope from your notes
Act as an estimator for a small residential builder. Using ONLY my notes below, write a home addition scope of work in this order: design, engineering and permits; site prep; foundation; framing; tie-in to the existing house; roofing and exterior; MEP; insulation, drywall and finishes; blending into the existing house; cleanup and closeout. For each, say what's included and who is responsible. Then list likely exclusions and assumptions. Do NOT add prices, dimensions, products, code or engineering details I didn't mention. Mark anything you need from me with [CHECK].
Notes:
[paste or dictate: addition type and size, plans, foundation, tie-in location, systems, finishes, site access]
Prompt 2: review the scope for gaps
Review this home addition scope before I price it. Using ONLY the text I paste, list: (1) things a homeowner might assume are included that aren't stated either way, (2) hidden-condition items without a unit price or allowance, (3) items not assigned to anyone (drawings, engineering, permits, zoning, selections), (4) items to confirm with the building department or an engineer. Don't add prices or code requirements.
Scope:
[paste]
Scopes, leveled sub bids and a proposal letter from your site notes
The AI Estimator Pack has copy-paste prompts and workflows for scopes by trade, takeoff checklists, sub bid leveling, pricing extras with your own rates, bid cover letters, estimate review and follow-ups, plus a spreadsheet template. AI organizes the paperwork. You set every number. One-time price.
What should a home addition scope of work include?
Who provides drawings and engineering, permits and zoning, site prep, foundation, framing, the tie-in to the existing house, roofing and exterior, electrical, plumbing and HVAC (including whether existing systems can carry the new load), insulation, drywall and finishes, allowances, unit prices for hidden conditions, cleanup and site restoration, plus exclusions and assumptions.
How do I handle hidden conditions where the addition ties into the existing house?
Many builders list unit prices for common tie-in repairs, such as framing or roof decking, and handle anything beyond those with a written change order before work continues. Set your own rates, and check your local and state requirements.
Should the scope say who is responsible for drawings and engineering?
Yes. Say who provides the drawings and any required engineering, who pays for them, and what happens to the price if plans change after permit review.
Write down where the new work starts, where the old house ends, and what a bad stud costs. Then open the wall.
Start with the free change order prompt, download the clause and text script at /free, see every role pack at /packs/, or get the full workflow.
Free: change order prompt
Paste it into ChatGPT, Claude or Gemini with your job note and get a short change order draft. No email needed. The free clause and text script is here.